Flip Out family entertainment centre, Telford
A trampoline and family entertainment centre over two floors inside Telford Shopping Centre, built while the centre kept trading.
- Value
- £1m
- Programme
- 28 weeks
- Peak site
- 35 operatives
- Result
- On time, on budget
Challenge
Two floors of former retail space turned into a leisure venue, inside a shopping centre trading throughout the works.
Approach
Deliveries in agreed windows, noisy work planned around trading hours and fire routes kept open every day. With 35 operatives at peak, daily coordination of trades and access was the job.
Result
Completed on the 28-week programme and within budget.



Scope
- Full demolition and M&E strip-out
- New partitions and fire-rated doors
- Servery and kitchen
- Changing rooms and party rooms
- Full exposed M&E installation
Project manager, delivered with WorkBox.
Discuss a project
Send the scope, location and programme. A reply with availability and terms follows the same working day.