Elliot Charles industrial subdivision, Leamington Spa
An 8,500 sqm portal-frame industrial building subdivided into separate units, taken over at month five after the management team resigned.
- Value
- £1.2m
- Building
- 8,500 sqm portal frame
- Joined
- Month five
- Result
- Practical completion
Challenge
Five months in, the team running the job resigned. The programme and commitments had to be picked up without the people who set them.
Approach
Relocated to site, established where the job stood against the programme and subcontract orders, and rebuilt the programme from there. Then ran it day to day to completion.
Result
Delivered to practical completion. WorkBox's own case study names Jack Irving as project manager.



Scope
- Subdivision of an 8,500 sqm portal-frame building
- Separation works between new units
- Services and fit-out to each unit
Project manager, delivered with WorkBox.